Ineke Steinhauer
Technical sectretary
ESIA in Uganda was first legislated in 1995, through the National Environment Act (NEA Cap 153). In March 2019, the new National Environment Act 2019 came into force. The Act contains provisions for SEA (Article 47) and for ESIA (Articles 110 to 116). The Act also contains schedules indicating projects that are subject to project briefs (Schedule 4), projects that require full ESIA (Schedule 5), sensitive areas that may lead to a full ESIA (Schedule 10) and projects that are exempt from ESIA (Schedule 11). The ESIA regulations have recently (December 2020) been revised and approved to be in line with the new Act. SEA regulations have been approved in April 2020 and SEA guidelines are also available. There is ample ESIA practice in Uganda and growing SEA practice. The National Environmental Management Authority is the coordinating, monitoring, regulatory and supervisory body. There is a certification system for ESIA consultants.
The National Environment (Environmental and Social) Regulations 2020, no. 143, 21th December 2020
The Ugandan ESIA regulations consider two types of procedures. Projects requiring submission of project briefs (=limited ESIA) and projects requiring full ESIA.
Projects for which project briefs are required according to Schedule 4, part I of the National Environment Act, 2019 can submit these directly to NEMA. NEMA will consult with lead agencies and will then take a decision on the project brief.
Projects for which project briefs are required according to Schedule 4, part II of the National Environment Act, 2019 can submit these directly to the applicable lead agency, who is then mandated to decide on the project brief.
For projects requiring project briefs, no scoping nor Terms of Reference are required.
Projects for which a full ESIA is mandatory (according to Schedule 5 and possibly Schedule 10 of the National Environment Act 2019) go through a more elaborate procedure, involving scoping/ToR, consideration of the ToR by NEMA (in consultation with lead agencies), undertaking the ESIA study including stakeholder consultation during the ESIA study. This results in the ESIA Statement, which is then submitted to NEMA. Review of the ESIA statement is done in consultation with the lead agencies and the general public and persons likely to be affected by the project. NEMA will then proceed to decision-making taking the review and consultation results into account. The decision will lead to an Environmental Certificate (of approval). In some cases NEMA may decide to hold a public hearing at the expense of the developer.
In some cases Environmental Risk Assessment is required as part of the ESIA (section 114 of the National Environment Act, 2019). This is for example the case when genetically modified organisms will be introduced.
NEMA may in liaison with the relevant lead agency, within 12 months of grant of a certificate of approval of the ESIA, arrange for onsite inspections and monitoring of the project to ensure compliance with the conditions in the Certificate of approval.
After the period of 12 months, the developer shall be subject to the requirements of the National Environment (Audit) Regulations.
National Environment Act, 2019 ESIA regulations no 143, December 2021Screening process
The National Environmental Act contains 4 Schedules to support the screening process.
Schedule 4, part I lists project that are required to submit a project brief to NEMA. Schedule 4, part II lists projects for which a project brief is required to be submitted to the relevant lead agency. Schedule 5 lists projects for which a full ESIA is required. Schedule 10 contains a list of sensitive areas. Whenever a project is located in or near such areas, a full ESIA may be required. Schedule 11 lists projects or activities exempted from ESIA.
The lists contain in most cases thresholds or provide location criteria.
In the case of project briefs: where NEMA and/or the lead agency is satisfied that the project is likely not to have significant adverse impacts on human health or the environment or that the project brief contains sufficient mitigation measures to cope with the anticipated impacts, it may approve the project. However, when the project is likely to have significant adverse impacts on the environment or that the project brief does not disclose sufficient mitigation measures to cope with anticipated impacts, the NEMA and/or lead agency may reject the project or may require the developer to undertake a full ESIA.
In the case of full ESIAs the developer shall proceed to the scoping stage.
Additionally, the National Environment (wetlands, riverbanks and lakeshores management) Regulations, 2000, require permits and EIAs to be obtained before undertaking any activities in wetlands, lakeshores and riverbanks.
National Environment Act, 2019 ESIA regulations 2020, article 6
Contents of the starting document
Whenever a project brief is required, this should describe:
Timeline Screening
For project briefs submitted for project listed under Schedule 4, part I, NEMA shall take a decision within 30 days of receipt of the full project brief.
For project briefs submitted for projects listed under Schedule 4, part II, the lead agency shall take a decision within 21 days of receipt of the full project brief
ESIA regulations 2020, articles 9 and 11
Scoping process
A developer of a project set out in Schedule 5 of the National Environment Act 2019 (or possibly projects listed in Schedule 10 of the Act), shall conduct a full ESIA by way of scoping, and prepare ToR for the ESIA. This is to be done in accordance with ESIA Guidelines issued by NEMA.
The ToR is reviewed by NEMA. NEMA may consult a lead agency or persons likely to be affected by the project, where necessary.
After review and acceptance of the ToR by NEMA, the developer will be advised to proceed to conducting the ESIA study. The approved ToR are valid for a period of six months from the date of approval or such other period as NEMA may specify in writing.
ESIA regulations, 2020, article 12
Contents of the scoping document
A ToR should be submitted, which reflects the results of the scoping exercise. The required contents are:
Timeline scoping
The developer shall submit the ToR to NEMA for consideration. Where NEMA is the developer, it shall submit its ToR to the technical committee on environment and social assessment.
Within 7 days of receipt NEMA shall:
ESIA regulations 2020, article 14
Assessment process
Upon approval of the terms of reference, the developer shall undertake the ESIA study, resulting in an ESIA report, which is supposed to be signed by all individuals who conducted the assessment.
The assessment process involves assessing the anticipated impacts (and benefits) of the project and proposing measures for avoidance, minimisation, mitigation or offsetting of negative impacts. In addition it is meant to provide an analysis of alternatives to enable decision-making regarding the project.
It is furthermore stated that the developer shall evaluate the proposed mitigation measures in accordance with the mitigation hierarchy, and may be required to develop offset or other compensation mechanisms associated with a project.
An environmental and social management and monitoring plan is also required and will be an integral part of the ESIA. The ESIA regulations provide minimum contents for such an ESMP in article 46.
Finally, it is prescribed that the developer shall, in undertaking the ESIA study, carry out consultations with relevant stakeholders, communities likely to be affected by the project and the public.
ESIA regulations, 2020, articles 15 and 16 and 46
Contents of the ESIA report
There is no indication of the required content of the ESIA report, other than a reference to Schedule 2 of the ESIA regulations. This 4 p. Schedule lists considerations that the developer should take into account, such as ecological, physical and social considerations.
It also states that where an environmental risk assessment is undertaken in tandem with the ESIA study, this shall be submitted as a section of the ESIA statement.
ESIA Regulations, 2020, Schedule 1 and article 17.
Accreditation of consultants
There is an accreditation system, and minimum standards and criteria for qualification of ESIA practitioners are laid down in the National Environment Regulations (Conduct and Certification of Environmental Practitioners), 2003. The website of NEMA provides a list of registered and certified environmental practitioners in Uganda (2018).
Review process
Upon receipt of the ESIA report, NEMA will send it to the relevant lead agencies for comment. Where the lead agency is the developer, the lead agency can not be part of the consultative process.
The lead agency reviews the ESIA report to ensure that it complies with the approved ToR, that all possible impacts have been identified and evaluated and that feasible mitigation measures have been proposed. It will also verify the findings and recommendations contained in the ESIA. The lead agency’s comments are then sent to NEMA.
The technical committee on environmental and social assessment shall handle lead agency consultations in respect to an ESIA submitted by NEMA.
NEMA may also invite the public in the area where the project is proposed to be located and communities likely to be affected by the project, to make oral or written comments on the ESIA.
NEMA will then review the ESIA based on:
NEMA or the technical committee on environmental and social assessment in respect of a project by NEMA, may, as part of the review conduct field visits to verify the information presented in the ESIA and may also engage external expertise.
NEMA may also determine whether a public hearing is necessary. For this, a set of criteria is listed in article 21.
ESIA regulations, 2020, articles 19-21
Review expertise
Relevant ministries and governmental agencies (lead agencies) and the public are involved in the review process. In some cases the technical committee on environmental assessment is involved. NEMA may also invite external experts to be involved in the review process.
Timeline Review
The lead agencies should submit their comments to NEMA within 21 days, or such other period as NEMA may specify in writing. Furthermore it is stated that the public and communities likely to be affected by the project shall provide comments to NEMA within the date indicated in the invitation. Furthermore in some occasions it may be decided to hold a public hearing. Therefore the timeline for review cannot be fixed.
Integration of ESIA into decision-making
The approval of the ESIA report automatically implies that a certificate of approval of ESIA will be awarded on payment of the fee prescribed in the regulations (article 49 and Schedule 4). Such a certificate of approval is required before any licensing authority issues a license for an activity. The ESIA approval is thus separate from licenses/permits for commencement of projects which are under the responsibility of different authorities. In some situations, NEMA also issues separate licenses, e.g. on wetlands, and on hazardous waste.
Article 4. mentions as a General prohibition that:
The competent authority in decision-making is the Executive Director of NEMA.
Where the developer does not commence activities within twelve months from the date of issuance of the certificate of approval or such further period as NEMA considers necessary, the certificate shall be rendered invalid and the developer shall be required to undertake a fresh environment assessment.
ESIA regulations, 2020, article 24 and 25 Schedule 3, Form 2 provides a standard format for the Environmental Certificate
Decision justification
Decisions are justified. For example, it is required that if the proposed project is rejected, the reasons for rejection should be communicated to the proponent in writing.
The decision is not required to be published to the public but any member of the public may request access to the record of the decision. Article 24 states that a copy of the decision may be made available to the public at the office of NEMA.
The developer is required to exhibit the certificate of approval and make available all the conditions of approval (article 52).
ESIA regulations, 2020, articles 24 and 52.
Timeline decision-making
NEMA shall conclude the process of consultation and consideration of the ESIA and make a decision within 60 days from the date of receipt of the complete ESIA from the developer.
Possibilities for appeal
Appeals can be made to the high court
Appeals can be made against any decision of the Executive Director
Any aggrieved person or institution has the right to make an appeal
These provisions are part of the National Environment Act 2019
Compliance monitoring
NEMA may, in liaison with the relevant lead agency, within 12 months of grant of a certificate of approval arrange for onsite inspections and monitoring of the project to ensure compliance with the conditions in the certificate of approval of the ESIA.
After the period of 12 months from grant of certificate of approval, the developer shall be subject to the requirements of the National Environment (Audit) Regulations no. 47, 2020.
A developer shall monitor the project and any environmental phenomena of the project:
Where an environmental and social management and monitoring plan is required as part of an ESIA,
the developer or operator shall monitor the project against the measurable actions and targets of this plan.
NEMA or a lead agency may, where there is public interest or cause to believe that a project has or may have adverse impacts on human health or the environment carry out an environmental enforcement audit or instruct the developer to carry out an environmental compliance audit, within a specified period determined by NEMA.
The proponent is required to undertake an initial environmental audit (by a specified date, which is between 12 to 36 months after commencement of the project) carried out by persons whose names and qualifications have been approved by the Executive Director of NEMA. Subsequently, the Executive Director may require other audits at any other time. After each audit, an environmental audit report shall be prepared by the developer and submitted to the Executive Director.
There are possibilities for external monitoring. Inspectors, “gazetted” by NEMA, may conduct inspections at any time. In addition inspection can be undertaken by lead agencies for areas under their jurisdiction. The public may, after showing reasonable cause, request that an environmental audit be carried out.
ESIA regulations, 2020, articles 53 and 54 Part XII of the National Environment Act, on environmental compliance and enforcement. National Environment (Audit) Regulations, no. 47, 2020
Non-compliance penalties
NEMA may cancel the certificate of approval where:
Article 56 of the ESIA regulations specifies in which cases someone commits an offence and is liable on conviction to a fine or imprisonment not exceeding 5 years, or both.
The National Environmental Act of 2019 states additional reasons for non-compliance.
The National Environment Act, 2019, Part XVI on Offences, Penalties, Fees, Fines and other Charges. ESIA regulations, 2020, articles 29 and 56
Public participation requirements for ESIA process stages
There are provisions for public participation. The public can participate during the stages of the project brief, scoping/ToR, ESIA study and ESIA report review.
The ESIA regulations (article 16) require the proponent to take all necessary measures to seek the views of affected people during the assessment stage, through:
During the review phase of the ESIA, NEMA may invite the public in the area the project is proposed to be located and communities likely to be affected by the project, to make oral or written comments on the ESIA statement. The ESIA regulations (article 20) contain requirements concerning how the invitation should be carried out.
NEMA shall during the consideration of the ESIA, determine whether a public hearing is necessary. This depends on:
Article 22 of the ESIA regulations describes how such a public hearing should be conducted. Such public hearing will be led by a presiding officer, who shall submit a report of the public hearing to NEMA (article 23).
Both oral and written comments can be given. Comments on the ESIA report are submitted in writing while during a public hearing formal presentations (written) and informal presentation (verbal) may be given to the NEMA presiding officer.
NEMA is required to take into account the comments on the ESIA report and all comments made in a public hearing. When a project is approved, it is not required to specifically address the public comments in the decision statement. When a project is rejected, public comments that have contributed to the rejection may be mentioned.
The public has to pay to obtain a summary/report of the public hearing and to obtain a copy of the ESIA report, although copies should also be available at a local library at no cost. On ocassion, digital copies are provided upon request.
ESIA regulations, articles 13, 16, 20, 22 and 23
Timeline for public comments
The public and communities likely to be affected by the project shall provide comments to NEMA within the date indicated in the invitation.
Whenever a public hearing is held, which must be announced at least two weeks in advance, the presiding officer shall submit a report of the public hearing to NEMA within seven days from the conclusion of the public hearing.
NEMA may issue guidelines for public hearings.
ESIA regulations, 2020, articles 20-23
Access to information
Subject to the Constitution and Access to Information Act, 2005, documents pertaining to the environmental and social impact assessment process submitted to NEMA shall be public documents. A person who desires to access the documents shall apply to NEMA and pay the prescribed fee.
The invitation for comments is published in a newspaper having nation-wide circulation or a newspaper having local circulation in the area the project is proposed to be located. In addition, through announcements on radios with local coverage, on the NEMA website and other relevant websites; or by distributing the necessary information about the proposed project through local authorities, in the languages understood by the majority of the affected people.
A public hearing is advertised through radio and print media in the locality of the project and through a national newspaper and radio. If a public hearing is held, multiple sessions may be organized at multiple locations. At least one session should be held in the community located nearest to the site of the proposed project.
The developer is required to exhibit the certificate of approval of environmental and social assessment and make available all the conditions of approval.
ESIA regulations, article 20, 22, 51 and 52