SEA profile
Updated to: 22 August 2019
Download as PDFOverview SEA procedure
The SEA procedure in DRC includes screening, scoping and the actual assessment.
The ACE is responsible for the screening decision.
Screening takes place at the planning phase of the PPP. The planning entity that is formulating the PPP is responsible to conduct the SEA.
Establishing context
Screening process
The SEA procedure starts when the entity that is planning the policy, plan and programme submits a screening request to the ACE. This is supposed to be done according the procedure outlined in operational manuals of the ACE. The ACE decides whether an SEA is needed and informs the planning entity about its decision.
Identification of stakeholders
The scoping report needs to include among others information on stakeholders.
Implementing SEA
Scoping process
When SEA is required, the planning entity hires a consultant to start with scoping. Any international consultant hired, must be associated to a national consultant.
Within 3 months from receiving it, the ACE must review the scoping report and notify the planning entity whether the scoping is approved, conditionally approved or rejected. If the three months are surpassed, the scoping report is considered as approved. If conditionally approved, the planning entity must re-submit the revised scoping report within 3 months from ACE’s notification. Otherwise, the scoping report is rejected. The same procedure and timelines for scoping are also applicable for the SEA report.
Baseline data
Baseline data is supposed to be included in the SEA report.
Alternatives
Alternatives need to be included in the scoping report.
Decree 14/019
Assessment/mitigation of effects
The assessment of impacts and mitigation measures need to be studied and included in the SEA report.
Content of SEA report
The SEA report should contain:
- Baseline information.
- Identification of environmental opportunities and constraints.
- Identification and evaluation of impacts and potential opportunities.
- Performance indicators, mitigation and optimization measures.
- Conclusions and recommendations.
Review process
The ACE establishes a panel of experts to review the scoping document. This panel consists of:
- 4 representatives of the ACE and the ministries. concerned with the policy, plan or programme.
- 1 expert from the National Fund for Promotion and Social Service.
- 2 resource persons identified based on their expertise.
Participation in review
The provisions for public hearing seem to apply only for ESIA as public hearings are demanded for projects or activities.
Articles 51-60 of Decree 14/019
Informing decision making
SEA and planning decision-making
When an SEA is approved, the ACE provides the planning entity an environmental advice, declaring that the PPP must be executed conform environmental and social safeguard principles.
Follow-up
SEA practice
Background information
Legal framework
Enabling law
In DRC, the general environmental law outlines the principles for environmental protection and governance. This law refers to the need to include environmental and social considerations in decision making and calls for sustainable development and public participation. Article 19 makes reference to the need to conduct of SEA for policies, plans and programmes (PPP).
no 11/009 of July 2011
http://www.ilo.org/dyn/natlex/docs/SERIAL/96987/114901/F-2083192176/COD-96987.pdf
National detailed regulation
Decree 14/019 sets out the procedural requirements for SEA. The same decree also provides requirements for ESIA, environmental audits and public hearings.
Scope of application
Article 19 of the environmental law states that an environmental evaluation is required before a policy, plans and programme (which may have environmental impacts) is formulated at state, provincial and decentral levels, by a public institution.
Article 4 of Decree 14/019 specifies that SEA is required for activities in the following sectors; infrastructure, hydrocarbons, mining, energy, telecommunications, industry, land, forest, agriculture and breeding, urban and rural development, transport, tourism and hotel development, health and all other commercial activities with potential environmental impacts.
Exemptions from application
The regulation does not provide for exemptions, but states that environmental studies for PPP's for military or or civil protection purposes do not belong to the public domain but to secret defense.
Institutional setting
Central SEA authority
The authority for SEA is ACE (l’Agence Congolaise de l’Environnement) under the Ministry of Environment and Sustainable Development. ACE is the central authority in DRC to promulgate specific regulations, operational procedures and guidelines for SEA.
(De)centralisation of SEA mandates
If the PPP in question is formulated at a decentralised level, it is the respective decentralised entity who is responsible for the SEA.