Chad

Legislation at project level

The constitution of Chad guarantees a healthy environment for everyone and stipulates that the State and the decentralized territorial authorities must take care of the protection of the environment. In 2010 a decree regulating environmental impact studies was introduced, followed by a guide in 2012.

The NCEA is not aware of legislation on SEA in Chad.

Overview ESIA procedure

The ESIA guide stipulates six phases of the administrative procedure:

  • Preparation and transmission of a project directive. This directive indicates the nature, scope and extent of the ESIA;
  • The completion of the ESIA by the Contracting Authority, in compliance with the directive;
  • Inform the public about the project to allow them to participate in the decision-making process. The public can obtain all the necessary information regarding the content of ESIAs;
  • Examination of the ESIA and judgment (in order to issue the Approval);
  • Transmission of the ESIA report and the approval to the competent authority for a final decision;
  • Environmental monitoring, carried out by the contracting authority, in collaboration with the ministry in charge of the environment.



Guidelines on EIA procedure (arrêté 039)

Click on a process step to learn more

Screening


Screening process
The client must prepare a document stating his intention to carry out a project. The document describes the general nature of the project and presents general information.

Scoping


Scoping process
The directorate in charge of impact studies has the task of approving the terms of reference for project impact studies.


Contents of the scoping document

The project owner prepares the Terms of Reference (ToR). The ToR are based on general and sector-specific guides, which are sent to the contracting authority by the ministry in charge of the environment.


Timeline scoping

The ministry in charge of the environment has 14 working days to approve the ToR.

Assessment


Contents of the ESIA report

  • An executive summary (must be presented separately);
  • A precise description of the project including information relating to its site and the criteria used for its selection, design and dimensions;
    the objectives and the justification of the project;
  • An analysis of the initial state of the site and its environment;
  • The measures likely to be taken to remedy the negative effects of the project on the environment, and if possible compensate for the damaging consequences of the project on the environment;
  • Analysis of toxicological risks and risks of technological accidents;
    emergency measures in the event of an accident;
  • Alternatives to the project, if any, or possible variants of the project;
    subsequent project phases and related projects;
  • A specification drawn up by the competent authority retraces in detail the conditions required to benefit from an authorization depending on the case;
    an environmental management plan including monitoring and follow-up activities, during and after the completion of the project.


Accreditation of consultants

Applications for formal accreditation from consultants are processed by the ministry in charge of the environment. It retains a directory of approved consultants for ESIAs.

Décret 630-2010

Review


Review process
After the EIA is submitted to the ministry in charge of the environment, it has 15 days to determine its admissibility.

Subsequently, the ministry organizes a public consultation, where everyone has the opportunity to express themselves on the subject and to indicate the collective values that are important for decision-making.

After the public consultation, the client has one month to respond to comments and review the ESIA.

The ministry then analyzes the ESIA, in consultation with the ministries and other bodies concerned. The ministry sets up a specific working committee for each EIA.

Guidelines on EIA procedure (arrêté 039)

Timeline Review

After the submission of the ESIA, the ministry has 3 months to express itself on the report. This deadline includes public consultation.

Décret 630-2010

Decision-making


Integration of ESIA into decision-making
As described above, the competent authority makes the decision, based on the approval of the Ministry of the Environment. Without the environmental permit, the competent authority cannot authorize a project.


Decision justification

The opinion of the ministry in charge of the environment takes into account the technical components (nature, intensity, duration of impacts, etc.) and the results of the public consultation. The decision is based on the EIA, the public consultation report, the report of the specific working committee.

Guidelines on EIA procedure (arrêté 039)

Follow-up


Compliance monitoring
Environmental monitoring of projects is the responsibility of the ministry in charge of the environment. Monitoring ensures the sufficiency and effectiveness of mitigation measures. The terms of the monitoring program are contained in the Environmental Management Plan (EMP).

Guidelines on EIA procedure (arrêté 039)


Non-compliance penalties

The types of offenses are described in Decree 630 and include projects without authorization, unauthorized design offices, non-compliance with technical prescriptions, etc.

Violations are punished either with the termination of the project or according to the laws in force.

Stakeholder engagement


Public participation requirements for ESIA process stages
Public participation is included in the EIA review.

Décret 630-2010


Timeline for public comments

After submission of the EIA, the ministry in charge of the environment brings it to the attention of the public. The consultation is open for a period of 45 days. Anyone interested has 30 days to request access to the entire EIA report.